Transformer lead times

Power transformers average 128 weeks from order to delivery (Q2 2025, Wood Mackenzie). Generator step-up units passed 160 weeks in Q1 2026. Before the pandemic, both took 30 to 60.

Lead time rating

US market · checked

Power transformer

128 weeks

Average, Q2 2025 · Wood Mackenzie

Source quote
“Power transformer lead times eased in Q2 falling by 10 weeks to an average of 128 weeks.”

Wood Mackenzie: Making the connection: meeting the electric T&D supply chain challenge, Executive Summary, September 2025 (with American Clean Power) · record

Generator step-up (GSU)

160+ weeks

More than, Q1 2026 · Wood Mackenzie (Ben Boucher, via Reuters)

Source quote
“Generator step-up transformer lead times surpassed 160 weeks by the first quarter of 2026, compared with an average of 143 weeks in 2024, while for high-voltage circuit breakers, they climbed to 125 weeks in the second half of last year, versus 77 weeks in 2023, according to Boucher.”

Reuters via Kitco: US power companies scramble to secure equipment as surging data center demand strains supplies (9 Jul 2026) · record

Price
+85.9% US transformer producer prices, Jan 2020 to Sep 2026. Our calculation from BLS series PCU335311335311.
Before 2020
30–60 weeks for large power and GSU units (Wood Mackenzie (via POWER)).
Serial
TLT-2026.11 · 60 observations · CC BY 4.0
2021 · All sizes: 50 weeks (Wood Mackenzie data cited in NIAC report) 50 2024 · All sizes: 120–210 weeks (NIAC) Apr 2024 · All sizes: 115–130 weeks (Wood Mackenzie) 2018 · Distribution, all: 12–14 weeks (Latitude Media) 12–14 2024 · GSU: 143 weeks (Wood Mackenzie) Q1 2025 · GSU: 147.7 weeks (Wood Mackenzie) Q1 2026 · GSU: 160+ weeks (Wood Mackenzie) Q2 2025 · GSU: 143.4 weeks (Wood Mackenzie) ≠ 2019 · Large power: 30–60 weeks (Wood Mackenzie) Q4 2023 · Large power: 120–130 weeks (Wood Mackenzie) May 2026 · Large power: 200+ weeks (Transformer Technology) Apr 2024 · Large power: 120–210 weeks (Wood Mackenzie) ≠ Apr 2024 · Large power: 80–120 weeks (Wood Mackenzie) ≠ Aug 2026 · Large power: 160+ weeks (VAWN) ≠ Q1 2025 · Large power: 138.4 weeks (Wood Mackenzie) Q2 2025 · Large power: 128 weeks (Wood Mackenzie) Q1 2025 · Pad-mount 1-phase: 19.9 weeks (Wood Mackenzie) ≠ Q2 2025 · Pad-mount 1-phase: 24 weeks (Wood Mackenzie) ≠ Aug 2026 · Pad-mount 3-phase: 40+ weeks (Giga Energy) 40+ Q1 2025 · Pad-mount 3-phase: 30 weeks (Wood Mackenzie) ≠ Q2 2025 · Pad-mount 3-phase: 46.4 weeks (Wood Mackenzie) ≠ 2020 · All sizes: 4–6 weeks (NEMA) 4–6 2022 · Distribution, all: About 12 months average; some quotes over three years; +429% vs pre-2021 (American Public Power Association) 2023 · Distribution, all: 12 months or more (vs three months in 2018) (American Public Power Association) 2024 · Distribution, all: Over two years (vs three months in 2018) (American Public Power Association) Feb 2024 · Distribution, all: Up to two years (4x pre-2022) (NREL) 2020 · Distribution, all: About two to three months pre-2021 (American Public Power Association) 2024 · Large power: Up to 60 months (US DOE) May 2026 · Large power: As long as four years (PwC analysts) May 2026 · Large power: Approximately 2.5 to 3 years for a typical 100 MVA unit; up to 5 years for extra-high-voltage units (National Laboratory of the Rockies (formerly NREL), US DOE) 2023 · Large power: 30 to 36 months from purchase order to receipt (up from 12 to 18 months) (US GAO) Jul 2026 · Large power: Pushing past three years (Reuters) Feb 2026 · Large power: More than doubled compared with 2019 (BloombergNEF) Feb 2024 · Distribution, all: As long as two years for single- and three-phase pad-mount units (Latitude Media) Feb 2025 · Pad-mount 3-phase: Double or triple pre-pandemic lead times (Hitachi Energy) May 2024 · Large power: Lead times have doubled (no week figure) (Transformer Technology) Feb 2025 · All sizes: Up to three years (NEMA) May 2024 · All sizes: 1 to 3 years (from 12 to 24 weeks earlier) (Thunder Said Energy) Feb 2025 · Large power: Three to six years (Hitachi Energy) 2021 · All sizes: 50 weeks (Wood Mackenzie data cited in NIAC report) 50 2024 · All sizes: 120–210 weeks (NIAC) Apr 2024 · All sizes: 115–130 weeks (Wood Mackenzie) 2018 · Distribution, all: 12–14 weeks (Latitude Media) 12–14 2024 · GSU: 143 weeks (Wood Mackenzie) Q1 2025 · GSU: 147.7 weeks (Wood Mackenzie) Q1 2026 · GSU: 160+ weeks (Wood Mackenzie) Q2 2025 · GSU: 143.4 weeks (Wood Mackenzie) ≠ 2019 · Large power: 30–60 weeks (Wood Mackenzie) Q4 2023 · Large power: 120–130 weeks (Wood Mackenzie) May 2026 · Large power: 200+ weeks (Transformer Technology) Apr 2024 · Large power: 120–210 weeks (Wood Mackenzie) ≠ Apr 2024 · Large power: 80–120 weeks (Wood Mackenzie) ≠ Aug 2026 · Large power: 160+ weeks (VAWN) ≠ Q1 2025 · Large power: 138.4 weeks (Wood Mackenzie) Q2 2025 · Large power: 128 weeks (Wood Mackenzie) Q1 2025 · Pad-mount 1-phase: 19.9 weeks (Wood Mackenzie) ≠ Q2 2025 · Pad-mount 1-phase: 24 weeks (Wood Mackenzie) ≠ Aug 2026 · Pad-mount 3-phase: 40+ weeks (Giga Energy) 40+ Q1 2025 · Pad-mount 3-phase: 30 weeks (Wood Mackenzie) ≠ Q2 2025 · Pad-mount 3-phase: 46.4 weeks (Wood Mackenzie) ≠ 2020 · All sizes: 4–6 weeks (NEMA) 4–6 2022 · Distribution, all: About 12 months average; some quotes over three years; +429% vs pre-2021 (American Public Power Association) 2023 · Distribution, all: 12 months or more (vs three months in 2018) (American Public Power Association) 2024 · Distribution, all: Over two years (vs three months in 2018) (American Public Power Association) Feb 2024 · Distribution, all: Up to two years (4x pre-2022) (NREL) 2020 · Distribution, all: About two to three months pre-2021 (American Public Power Association) 2024 · Large power: Up to 60 months (US DOE) May 2026 · Large power: As long as four years (PwC analysts) May 2026 · Large power: Approximately 2.5 to 3 years for a typical 100 MVA unit; up to 5 years for extra-high-voltage units (National Laboratory of the Rockies (formerly NREL), US DOE) 2023 · Large power: 30 to 36 months from purchase order to receipt (up from 12 to 18 months) (US GAO) Jul 2026 · Large power: Pushing past three years (Reuters) Feb 2026 · Large power: More than doubled compared with 2019 (BloombergNEF) Feb 2024 · Distribution, all: As long as two years for single- and three-phase pad-mount units (Latitude Media) Feb 2025 · Pad-mount 3-phase: Double or triple pre-pandemic lead times (Hitachi Energy) May 2024 · Large power: Lead times have doubled (no week figure) (Transformer Technology) Feb 2025 · All sizes: Up to three years (NEMA) May 2024 · All sizes: 1 to 3 years (from 12 to 24 weeks earlier) (Thunder Said Energy) Feb 2025 · Large power: Three to six years (Hitachi Energy)
Large power GSU Pad-mount 3φ Pad-mount 1φ Distribution, all All sizes Weeks from order to delivery. Click any mark for the source’s own words. How to read the marks

Q2 2025 Power transformer 128 weeks

“Power transformer lead times eased in Q2 falling by 10 weeks to an average of 128 weeks.”

Wood Mackenzie · Wood Mackenzie: Making the connection: meeting the electric T&D supply chain challenge, Executive Summary, September 2025 (with American Clean Power) read 2026-11-09 · record

Where lead times stand now

All 60 readings

The transformer shortage is a large-unit problem now. Distribution lead times came down from their 2022–2024 peaks of up to two years, while power transformers and GSUs kept climbing: Wood Mackenzie’s quarterly survey shows power units easing to 128 weeks in Q2 2025 and GSUs breaking 160 weeks in Q1 2026. Plan a substation or a generator interconnection around three years of transformer lead time, and a pad-mount around a year.

ClassLatest readingAlso reportedBefore the shortage
Large power 128weeks Q2 2025 · Wood Mackenzie Pushing past three years Jul 2026 · Reuters (Roseville Electric CEO Dan Beans) 30–60 weeks 2019 · Wood Mackenzie (via POWER)
Generator step-up (GSU) 160+weeks Q1 2026 · Wood Mackenzie (Ben Boucher, via Reuters) 143.4 weeks Q2 2025 · Wood Mackenzie 30–60 weeks 2019 · Wood Mackenzie (via POWER) (large power and GSU combined)
Pad-mount, 3-phase 46.4weeks Q2 2025 · Wood Mackenzie 40+ weeks Aug 2026 · Giga Energy No pre-2021 week figure for this class
Pad-mount, 1-phase 24weeks Q2 2025 · Wood Mackenzie 19.9 weeks Q1 2025 · Wood Mackenzie No pre-2021 week figure for this class
Distribution, all types Over two years (vs three months in 2018) 2024 · American Public Power Association Up to two years (4x pre-2022) Feb 2024 · NREL (via pv magazine USA) 12–14 weeks 2018 · Latitude Media (Catalyst podcast, ERMCO CEO Tim Mills)
Pole-mount, on its own No published lead-time figure for pole-mount units alone. APPA and NREL report distribution transformers as one group; Wood Mackenzie publishes pole-top prices (+21% from Jan 2023 to Mar 2025) but no pole-top lead time. Send us one

Every observation

CSV · JSON

60 of 60 observations

Type and sizeAs the source states itSourceQuote
Sep 2026–PricesElectric power and specialty transformers (industry PPI)AllUS+85.9% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
Aug 2026≠160+Large powerPower / substation transformerPower / substationUS160+ weeks; index says this is Wood Mackenzie's 2026 read (aggregator, not primary)VAWN (aggregating Wood Mackenzie) · weak sourceusevawn.com
Aug 202640+Pad-mount 3-phasePad-mount three-phase distribution transformerPad-mounted 3-phase (data center spec)US40-plus weeks (supplier's field observation)Giga Energygigaenergy.com
Jul 2026mo/yrLarge powerLarge substation transformerLarge substationUSPushing past three yearsReuters (Roseville Electric CEO Dan Beans)kitco.com
May 2026mo/yrLarge powerHigh-capacity power transformerHigh capacityUSAs long as four yearsPwC analysts (via pv magazine, citing Reuters Events)pv-magazine.com
May 2026mo/yrLarge powerLarge power transformerTypical LPT (100 MVA); extra-high-voltage up to 5 yearsUSApproximately 2.5 to 3 years for a typical 100 MVA unit; up to 5 years for extra-high-voltage unitsNational Laboratory of the Rockies (formerly NREL), US DOEnlr.gov
May 2026200+Large powerLarge power transformerLargeUS/EUUp to 200 weeks in critical cases; attributed to Northfield Transformers (a vendor) - weak sourceTransformer Technology (citing Northfield Transformers) · weak sourcetransformer-technology.com
Q1 2026160+GSUGenerator step-up (GSU)GSUUSMore than 160 weeksWood Mackenzie (Ben Boucher, via Reuters)kitco.com
Feb 2026mo/yrLarge powerLarge power transformer100 MVA and aboveUSMore than doubled compared with 2019BloombergNEF (via pv magazine)pv-magazine.com
Jan 2026–PricesElectric power and specialty transformers (industry PPI)AllUS+78.4% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
Q2 2025≠143.4GSUGenerator step-up (GSU)GSUUSAverage 143.4 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Q2 2025128Large powerPower transformerPower transformer (classified by type, not voltage)USAverage 128 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Q2 2025≠24Pad-mount 1-phasePad-mount single-phase distribution transformerPad-mounted 1-phaseUSAverage 24 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Q2 2025≠46.4Pad-mount 3-phasePad-mount three-phase distribution transformerPad-mounted 3-phaseUSAverage 46.4 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Mar 2025–PricesPole-mounted distribution transformerPole-topUS+21% vs January 2023 (index Jan 23 = 100)Wood Mackenziepowermag.com
Mar 2025–PricesPower transformerPower transformerUS+15% vs January 2023 (index Jan 23 = 100)Wood Mackenziepowermag.com
Mar 2025–PricesPad-mount single-phase distribution transformerSingle-phase pad-mountUS+18% vs January 2023 (index Jan 23 = 100)Wood Mackenziepowermag.com
Mar 2025–PricesSubstation transformerSubstation transformerUS+8% vs January 2023 (index Jan 23 = 100)Wood Mackenziepowermag.com
Mar 2025–PricesPad-mount three-phase distribution transformerThree-phase pad-mountUS+20% vs January 2023 (index Jan 23 = 100)Wood Mackenziepowermag.com
Q1 2025147.7GSUGenerator step-up (GSU)GSUUSAverage 147.7 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Feb 2025mo/yrPad-mount 3-phasePad-mounted distribution transformerPad-mountedUSDouble or triple pre-pandemic lead timesHitachi Energy (via Utility Dive)utilitydive.com
Q1 2025138.4Large powerPower transformerPower transformer (classified by type, not voltage)USAverage 138.4 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Q1 2025≠19.9Pad-mount 1-phasePad-mount single-phase distribution transformerPad-mounted 1-phaseUSAverage 19.9 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Q1 2025≠30Pad-mount 3-phasePad-mount three-phase distribution transformerPad-mounted 3-phaseUSAverage 30 weeks after receipt of order (chart value).Wood Mackenziepowermag.com
Feb 2025mo/yrAll sizesTransformer (unspecified)UnspecifiedUSUp to three yearsNEMA (via Utility Dive)utilitydive.com
Feb 2025mo/yrLarge powerTransmission-scale power transformerTransmission scaleUSThree to six yearsHitachi Energy (via Utility Dive)utilitydive.com
Jan 2025–PricesElectric power and specialty transformers (industry PPI)AllUS+69.6% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
2025–PricesDistribution transformerDistribution (some classes)USup to +95% vs 2019Wood Mackenzie (via POWER)powermag.com
2025–PricesGenerator step-up (GSU)GSUUS+45% vs 2019Wood Mackenzie (via POWER)powermag.com
2025–PricesLarge power transformerLPTUS+50–70% vs 2019Wood Mackenzie (2025), cited by the National Laboratory of the Rockies (May 2026)docs.nlr.gov
2025–PricesPower transformerPower transformerUS+77% vs 2019Wood Mackenzie (via POWER)powermag.com
May 2024mo/yrLarge powerTransformers (general)UnspecifiedEULead times have doubled (no week figure)Transformer Technology (quoting Ghent University)transformer-technology.com
May 2024mo/yrAll sizesTransformers (general)Unspecifiedglobal1 to 3 years (from 12 to 24 weeks earlier)Thunder Said Energythundersaidenergy.com
Apr 2024115–130All sizesTransformers (average)All sizesUSAverage of 115 to 130 weeksWood Mackenzie (via POWER)powermag.com
Apr 2024≠120–210Large powerSubstation power and GSULargeUS120 to 210 weeks (2.3 to 4 years). Utility Dive reports the same April report as 80 to 120 weeks for larger transformers; NIAC/others cite 80 to 210.Wood Mackenzie (via POWER)powermag.com
Apr 2024≠80–120Large powerLarger power transformersLargeUS80 to 120 weeks, as reported by Utility Dive; conflicts with POWER's 120 to 210Wood Mackenzie (via Utility Dive)utilitydive.com
Apr 2024–PricesTransformers (all)All sizesUS+60–80% vs January 2020Wood Mackenzie (via POWER)powermag.com
Feb 2024mo/yrDistribution, allDistribution transformerDistributionUSUp to two years (4x pre-2022)NREL (via pv magazine USA)pv-magazine-usa.com
Feb 2024mo/yrDistribution, allPad-mounted distribution transformerPad-mount (single- and three-phase)USAs long as two years for single- and three-phase pad-mount unitsLatitude Media (ERMCO CEO Tim Mills)latitudemedia.com
Jan 2024–PricesElectric power and specialty transformers (industry PPI)AllUS+67.8% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
2024120–210All sizesTransformers (all, procurement)All sizes; largest up to 210 weeksUS120 weeks average; largest units up to 210 weeksNIAC (via Utility Dive)utilitydive.com
2024–PricesDistribution and large power transformersAllUS+40% vs 2020, inflation-adjustedCongressional Research Service (BLS data)everycrsreport.com
2024mo/yrDistribution, allDistribution transformerAll voltage classesUSOver two years (vs three months in 2018)American Public Power Associationpublicpower.org
2024mo/yrLarge powerExtra-high-voltage large power transformerExtra-high-voltage (EHV)USUp to 60 monthsUS DOE (2024), cited by the National Laboratory of the Rockies (May 2026)docs.nlr.gov
2024143GSUGenerator step-up (GSU)GSUUSAverage of 143 weeksWood Mackenzie (Ben Boucher, via Reuters)kitco.com
Q4 2023120–130Large powerLarge power transformer and GSULarge power / GSUUSAverage of 120 to 130 weeksWood Mackenzie (via POWER)powermag.com
Jan 2023–PricesPower and distribution transformers, except parts (product PPI)AllUS+65% vs January 2020 (index 201.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
Jan 2023–PricesElectric power and specialty transformers (industry PPI)AllUS+60.7% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
2023mo/yrDistribution, allDistribution transformerAll voltage classesUS12 months or more (vs three months in 2018)American Public Power Associationpublicpower.org
2023mo/yrLarge powerLarge power transformerTypical LPTUS30 to 36 months from purchase order to receipt (up from 12 to 18 months)US GAO (2023), cited by the National Laboratory of the Rockies (May 2026)docs.nlr.gov
Jan 2022–PricesPower and distribution transformers, except parts (product PPI)AllUS+36.8% vs January 2020 (index 201.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
Jan 2022–PricesElectric power and specialty transformers (industry PPI)AllUS+39.5% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
2022mo/yrDistribution, allDistribution transformerAll voltage classesUSAbout 12 months average; some quotes over three years; +429% vs pre-2021American Public Power Associationpublicpower.org
Jan 2021–PricesElectric power and specialty transformers (industry PPI)AllUS+2.5% vs January 2020 (index 255.5)US Bureau of Labor Statistics (via FRED)fred.stlouisfed.org
202150All sizesTransformers (all, procurement)All sizesUSAround 50 weeksWood Mackenzie data cited in NIAC report (via Utility Dive)utilitydive.com
2020mo/yrDistribution, allDistribution transformerAll voltage classesUSAbout two to three months pre-2021American Public Power Associationpublicpower.org
20204–6All sizesTransformer (unspecified)UnspecifiedUS'Five years ago' relative to Feb 2025; type not specifiedNEMA (via Utility Dive)utilitydive.com
201930–60Large powerPower transformer (substation and GSU)Large power / GSUUSPre-pandemic range, depending on specifications and sizeWood Mackenzie (via POWER)powermag.com
201812–14Distribution, allDistribution transformerDistribution (single- and three-phase)US12 to 14 weeks from purchase order to deliveryLatitude Media (Catalyst podcast, ERMCO CEO Tim Mills)latitudemedia.com
2010mo/yrLarge powerLarge power transformer>100 MVA (LPT)US5 to 12 months (domestic), 6 to 16 months (foreign); 18 to 24 months in high-demand periodsUS DOE (2014 study, via ReliaMag)reliamag.com

22 readings stated in weeks, 18 in months or years, 20 on prices. ≠ marks a figure that named sources report differently; see conflicts. “As of” is the period the number describes, not the publication date.

Transformer prices

BLS series on FRED
+85.9%

US producer prices for electric power and specialty transformers, January 2020 to Sep 2026.

  1. Jan 2021 +2.5%
  2. Jan 2022 +39.5%
  3. Jan 2023 +60.7%
  4. Jan 2024 +67.8%
  5. Jan 2025 +69.6%
  6. Jan 2026 +78.4%
  7. Sep 2026 +85.9%

Calculated by us from BLS producer price index values for series PCU335311335311 (Electric Power and Specialty Transformer Manufacturing, not seasonally adjusted, via FRED): January 2020 = 255.5, September 2026 = 475.065. Each bar is the change against January 2020. BLS’s narrower product series for power and distribution transformers (PCU3353113353111) ran +36.8% by Jan 2022 and +65% by Jan 2023 before it stopped publishing in February 2023.

By class, from the analysts

≠GSUs in Q2 2025: 143 or 144 weeks?
Wood Mackenzie’s own executive summary says 143 weeks, and its chart label reads 143.4. POWER (Jan 2026) and most secondary sites print 144. We carry 143.4, the publisher’s figure.
≠The “30 weeks” for distribution in Q2 2025
CRS, Giga Energy and VAWN cite 30 weeks for distribution transformers in Q2 2025. Wood Mackenzie’s chart puts three-phase pad-mount at 30.0 weeks in Q1 and 46.4 in Q2, and single-phase at 19.9 then 24.0. Both changes match the quarter-on-quarter deltas the report states (+16.4 and +4.1), so we carry the chart values.
≠April 2024: 120–210 or 80–120 weeks?
POWER reported Wood Mackenzie’s April 2024 range for substation power and GSU units as 120 to 210 weeks. Utility Dive reported the same release as 80 to 120 weeks for larger transformers, and NIAC and others cite 80 to 210. Both readings are on the chart as hollow marks, and neither sits on the line.
≠160+ weeks for power transformers?
VAWN’s index (Aug 2026) reads Wood Mackenzie’s 2026 data as 160+ weeks for power and substation units. The only confirmed 160+ figure is for GSUs, from Wood Mackenzie’s Ben Boucher via Reuters. We plot VAWN’s read as a weak, hollow mark.

New transformer capacity

All 27 manufacturers

16 of the 27 manufacturers we track have a verified US plant. 16 have announced new capacity; the figures below are as each source reports them.

ManufacturerAnnounced capacityUS plant
Central Moloney New $50M Florida plant (POWER, Jan 2026). US plant verified
Eaton $340M three-phase transformer facility in South Carolina, targeting a 2027 start (POWER, Jan 2026). Not yet verified
ERMCO $70M-plus investments in Tennessee and Wisconsin (POWER, Jan 2026). US plant verified
Hammond Power Solutions Completed expansions in Mexico and at Guelph, Ontario in 2025 (2025 Annual Report). US plant verified
HD Hyundai Electric Second Alabama plant (groundbreaking March 2026), due for completion in April 2027, adding about 50% extra-high-voltage transformer capacity with production up to 765 kV (Korea Times, Oct 2026); aiming to raise US production 30% by 2026 (POWER, Jan 2026). US plant verified
Hitachi Energy $1.5B global transformer investment through 2027 (POWER 2024; Utility Dive 2025); $500M in North America through 2027 (Utility Dive 2025); $457M South Boston, Virginia LPT plant, set to be the largest US LPT plant by 2028; $106M Alamo, Tennessee components expansion; CA$270M Varennes, Quebec buildout to nearly triple LPT output (POWER, Jan 2026). US plant verified
Howard Industries $236.95M expansion in Clarke, Jones and Simpson counties, Mississippi, with 450 new jobs (SuperTalk Mississippi, Jun 2025). US plant verified
Hyosung Heavy Industries (Hyosung HICO) $300M expansion of the Memphis transformer plant (Korea Times, Oct 2026); HVDC transformer plant in Changwon, South Korea, scheduled for completion in 2027 (Wikipedia). US plant verified
LS Electric $240M across US manufacturing by 2030, including its Utah switchgear plant and a Bastrop, Texas campus; extra-high-voltage transformer sales up 106% in Q3 2026 (Korea Times, Oct 2026). Not yet verified
MGM Transformer 430,000-square-foot facility in Waco, Texas (POWER, Jan 2026). US plant verified
Prolec GE (GE Vernova) More than $300M across new and expanded sites, including a medium-power plant in Goldsboro, North Carolina, and more pad-mount capacity in Louisiana and Mexico (POWER, Jan 2026); $1B of Prolec GE capex planned for 2026–2028 and $5B of GE Vernova’s equipment backlog (GE Vernova Q3 2026 results). US plant verified
Schneider Electric Investing hundreds of millions of dollars in capacity expansion (Jeffrey DeSain, GM North American Transformer Business, Utility Dive 2025). Not yet verified
SGB-SMIT Group Acquired Southwest Electric Co. in the US (Jan 2025); opened the SGB-ALFA factory in Botoșani, Romania (Jul 2026); took a majority stake in COMEL Transformatori (Jul 2026) - headlines on sgb-smit.com. US plant verified
Siemens Energy $150M Charlotte, North Carolina LPT plant: 57 LPTs per year, 15,000 MVA (POWER 2024); production expected early 2027 (POWER, Jan 2026). US plant verified
Virginia Transformer Corp $40M expansion in Georgia to raise output 70% (POWER, Jan 2026); opened a Mexico plant in 2023 for units up to 100 MVA (POWER 2024). US plant verified
WEG Adding transformer capacity in Missouri (POWER, Jan 2026). US plant verified

Transformer shortage questions

How long is the lead time for a power transformer?

Wood Mackenzie’s supplier survey put power transformers at an average of 128 weeks after receipt of order in Q2 2025, down 10 weeks from Q1. Generator step-up units averaged 143 weeks that quarter and passed 160 weeks by Q1 2026 (Wood Mackenzie’s Ben Boucher, via Reuters). DOE’s National Laboratory of the Rockies puts a typical 100 MVA unit at 2.5 to 3 years and extra-high-voltage units at up to 5 years (2026). The largest transmission units take three to six years, according to Hitachi Energy (Feb 2025).

How long does a distribution transformer take?

Pad-mount units averaged 24 weeks for single-phase and 46.4 weeks for three-phase in Q2 2025 (Wood Mackenzie). That is down from peaks of up to two years in 2022–2024 (APPA, NREL). Before 2021 the norm was two to three months (APPA), and ERMCO quoted 12 to 14 weeks in 2018.

Why is there a transformer shortage?

Demand outran factory capacity. Since 2019, power transformer demand is up 119% and GSU demand up 274%, and Wood Mackenzie models a 2025 shortfall of 30% for power transformers and 10% for distribution units (POWER, Jan 2026). Data centers, renewables and grid replacement all draw on the same plants, and imports supply roughly 80% of the large power transformers the US uses (National Laboratory of the Rockies, DOE, May 2026).

How much have transformer prices risen?

US producer prices for transformer manufacturing rose 85.9% from January 2020 to September 2026: our calculation from BLS series PCU335311335311. Wood Mackenzie puts unit prices since 2019 at +77% for power transformers, +45% for GSUs and up to +95% for some distribution classes (POWER, Jan 2026).

Who is building new US transformer capacity?

Hitachi Energy is building a $457M large power transformer plant in South Boston, Virginia. Siemens Energy’s $150M Charlotte plant expects production in early 2027. Eaton is putting $340M into a three-phase plant in South Carolina, Virginia Transformer $40M into Georgia, ERMCO $70M-plus into Tennessee and Wisconsin, and Central Moloney $50M into a Florida plant (all via POWER, Jan 2026). Hyosung is putting $300M into its Memphis plant, and HD Hyundai Electric’s second Alabama plant adds about 50% more extra-high-voltage capacity from April 2027 (Korea Times, Oct 2026). All 27 manufacturers

Cite and reuse

Data and fields

The full dataset is open under CC BY 4.0. Use it in reports, decks, models and articles; credit Transformer Lead Times and link transformerleadtimes.com. Every row keeps its publisher, verbatim quote and access date, so you can cite the original too.

Download CSVDownload JSONManufacturers CSV

Transformer Lead Times (2026). Transformer lead times: dated, sourced observations, 2010–2026. Retrieved 9 Nov 2026, from https://transformerleadtimes.com/ (CC BY 4.0)